DCNS Completes CVN Charles de Gaulle Refit
31.07.2013 Europe
The French Navy’s Fleet Support Service (SSF) signed off on the completion of the intermediate refit of nuclear-powered aircraft carrier Charles de Gaulle after six months’ work by DCNS.
From hull to combat system, without forgetting compliance tests to the latest environmental standards, communications suite modernization or the refurbishment of the accommodation and recreation areas, the project involved some 950 people and 1 million person-hours’ work.
In addition to scheduled maintenance, the refit was used to undertake significant modernization. The work was performed in the Vauban drydock at the Toulon naval base. The ship was given a complete facelift that included the repainting of a total area of 26,000 square meters and the complete refurbishment of one of the main galleys.
Other modernization work included the replacement of the stabilization computer. The propulsion system and other shipboard systems and equipment were inspected, overhauled and tested to ensure optimal performance in operation. Some 35 kilometers of cabling was also installed with a view to the later installation of a state-of-the-art IP network.
CVN Charles de Gaulle underwent a thorough overhaul performed by teams assembled by DCNS and its partners, supported day-to-day by the ship’s crew.
“Scheduled refits are essential to return a ship to ‘as new’ condition. This six-month period of intense contract maintenance and modernization is over. Other teams will now resume shore-based day-to-day monitoring of the ship’s systems and equipment,” said Franck Bouffety, the Group’s Charles de Gaulle Program Manager.
With over 1,000 tasks in progress each week, the Vauban drydock was very busy indeed. Despite the huge number of jobs to be performed, everything was completed on time. DCNS completed the 6,000 maintenance and modernization ‘line tasks’ specified for this scheduled refit. In addition to the ship’s crew, all available staff based at the Toulon naval base were mobilized for the extended pit stop. Virtually every DCNS centre contributed in one way or another. In all, the Group assigned almost 500 employees to the project.
From hull to combat system, without forgetting compliance tests to the latest environmental standards, communications suite modernization or the refurbishment of the accommodation and recreation areas, the project involved some 950 people and 1 million person-hours’ work.
In addition to scheduled maintenance, the refit was used to undertake significant modernization. The work was performed in the Vauban drydock at the Toulon naval base. The ship was given a complete facelift that included the repainting of a total area of 26,000 square meters and the complete refurbishment of one of the main galleys.
Other modernization work included the replacement of the stabilization computer. The propulsion system and other shipboard systems and equipment were inspected, overhauled and tested to ensure optimal performance in operation. Some 35 kilometers of cabling was also installed with a view to the later installation of a state-of-the-art IP network.
CVN Charles de Gaulle underwent a thorough overhaul performed by teams assembled by DCNS and its partners, supported day-to-day by the ship’s crew.
“Scheduled refits are essential to return a ship to ‘as new’ condition. This six-month period of intense contract maintenance and modernization is over. Other teams will now resume shore-based day-to-day monitoring of the ship’s systems and equipment,” said Franck Bouffety, the Group’s Charles de Gaulle Program Manager.
With over 1,000 tasks in progress each week, the Vauban drydock was very busy indeed. Despite the huge number of jobs to be performed, everything was completed on time. DCNS completed the 6,000 maintenance and modernization ‘line tasks’ specified for this scheduled refit. In addition to the ship’s crew, all available staff based at the Toulon naval base were mobilized for the extended pit stop. Virtually every DCNS centre contributed in one way or another. In all, the Group assigned almost 500 employees to the project.
Previous PostFirst Tranche 3 Typhoon on the Move
Latest events
I/ITSEC 2024
02 - 06 Dec 2024Orlando, Florida - United Statesintersec 2025
14 - 16 Jan 2025World Trade Centre (WTC) Dubai - United Arab EmiratesIDEX & NAVDEX 2025
17 - 21 Feb 2025Abu Dhabi National Exhibition Centre - ADNEC - United Arab EmiratesDefence Exhibition Athens - DEFEA
06 - 08 May 2025Metropolitan Expo Athens - Greece